Planning Atlas
Planning AtlasBarking And DagenhamAbbey ward21/02125/FULL
Planning application · Barking And Dagenham

21/02125/FULL.

Land Off The A124, Barking, Barking And Dagenham, IG11 8JH

Full / Other Planning at Land Off The A124, Barking, Barking And Dagenham, IG11 8JH, received 24 Nov 2021 — approved on 30 Aug 2022 (delegated, Olivia St-Amour).

Barking And DagenhamAbbeyIG11 8JH21/02125/FULL
ApprovedRefusedOther
At a glance · this applicationBarking And Dagenham profile →
Approved
Outcome
30 Aug 2022
40 wks
Decision time
32 wks over the 8-week target
Conditions
not captured
50
Documents
50 linked
Objections
not captured
No
Appeal
none recorded
Record from the Barking And Dagenham planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Construction of a new above ground decentralised energy centre and visitor centre and associated buried heat network piping within the site, landscaping, parking, new site access, boundary treatments and illuminated external display. The Energy Centre building and site compound shall house mechanica

Reference
21/02125/FULL
Type
Full Planning Permission
Applicant
Agent / consultant
Case officer
Postcode
IG11 8JH
Ward
Received
24 Nov 2021
Validated
20 Dec 2021
Target date
2 Sep 2022
Decision date
30 Aug 2022
Decision route
Not recorded
Status
Decision Issued
Reference
21/02125/FULL
Type
Full Planning Permission
Show all 16 rows
Applicant
Agent / consultant
Case officer
Postcode
IG11 8JH
Ward
Received
24 Nov 2021
Validated
20 Dec 2021
Target date
2 Sep 2022
Decision date
30 Aug 2022
Decision route
Not recorded
Status
Decision Issued
Documents

What was filed?

Document
Published
View
DATED DECISION NOTICE
30 Aug 2022
Completed Legal Agreement- 30.08.2022
30 Aug 2022
Committee Report - Energy Centre - April 2022
4 May 2022
Site Selection Table - Revised
21 Mar 2022
Applicant Response Letter to Neighbour Representations
21 Mar 2022
Barking Town Centre Decarbonisation Pathway
21 Mar 2022
Transport Statement
6 Jan 2022
Planning Statement
20 Dec 2021
Energy Statement
20 Dec 2021
Townscape and Visual Appraisal - 81
24 Nov 2021
DATED DECISION NOTICE
30 Aug 2022
Completed Legal Agreement- 30.08.2022
30 Aug 2022
Committee Report - Energy Centre - April 2022
4 May 2022
Show all 10 rows
Site Selection Table - Revised
21 Mar 2022
Applicant Response Letter to Neighbour Representations
21 Mar 2022
Barking Town Centre Decarbonisation Pathway
21 Mar 2022
Transport Statement
6 Jan 2022
Planning Statement
20 Dec 2021
Energy Statement
20 Dec 2021
Townscape and Visual Appraisal - 81
24 Nov 2021

Documents open on the Barking And Dagenham portal. View the application page ↗

Decision

What happened?

Approved on 30 Aug 2022, delegated decision by Olivia St-Amour — 40 weeks from submission (32 over the 8-week target).

Timeline

Date
Event
24 Nov 2021
Application received
20 Dec 2021
Application validated
2 Sep 2022
Statutory target date
30 Aug 2022
Delegated decision: Approved · Olivia St-Amour
24 Nov 2021
Application received
20 Dec 2021
Application validated
2 Sep 2022
Statutory target date
Show all 4 rows
30 Aug 2022
Delegated decision: Approved · Olivia St-Amour

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent as stated on the application
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent as stated on the application
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.