Planning Atlas
Planning AtlasBexleySLADE GREEN & NORTH END wardDA8 3PW19/02727/FUL01
Planning application · Bexley

19/02727/FUL01.

47, 47A, 47B, 47C, 49, 49A, 49B, And 49C Northend Road Erith Kent DA8 3PW

Discharge of Conditions at 47, 47A, 47B, 47C, 49, 49A, 49B, And 49C Northend Road Erith Kent DA8 3PW, received 11 Jan 2021 — refused on 28 Jul 2023 (delegated, Ian Smith).

ApprovedRefusedOther
At a glance · this applicationBexley profile →
Refused
Outcome
28 Jul 2023
133 wks
Decision time
125 wks over the 8-week target
Conditions
not captured
19
Documents
19 linked
0
Objections
0 in support
No
Appeal
none recorded
Record from the Bexley planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Details of condition 3 (demolition/construction methodology) and 5 (retaining earthworks) pursuant to planning permission 19/02727/FUL for Demolition of existing properties and erection of a part two/part three/part five storey building comprising 1 x 1 bed, 7 x 2 bed and 1 x 3 bed apartments with a commercial unit at ground floor (Class D1), associated parking and amenity space.

Reference
19/02727/FUL01
Type
Details pursuant to Planning Condition
Agent / consultant
Case officer
Postcode
Council
Received
11 Jan 2021
Target date
8 Mar 2021
Decision date
28 Jul 2023
Decision route
Delegated (officer)
Status
Refused
Reference
19/02727/FUL01
Type
Details pursuant to Planning Condition
Show all 15 rows
Agent / consultant
Case officer
Postcode
Council
Received
11 Jan 2021
Target date
8 Mar 2021
Decision date
28 Jul 2023
Decision route
Delegated (officer)
Status
Refused
Documents

What was filed?

Document
Published
View
DECISION LETTER
28 Jul 2023
CASE SHEET
28 Jul 2023
AIP - SUBMISSION COMMENTS FORM
11 Apr 2022
CMP
29 Sept 2021
UPDATED CEMP
18 Mar 2021
UPDATED CONSTRUCTION MANAGEMENT PLAN
5 Mar 2021
UPDATED CONSTRUCTION MANAGEMENT PLAN
5 Mar 2021
UPDATED CONSTRUCTION MANAGEMENT PLAN
5 Mar 2021
UPDATED RISK ASSESSMENT METHOD STATEMENT
4 Mar 2021
UPDATED RISK ASSESSMENT METHOD STATEMENT
4 Mar 2021
DECISION LETTER
28 Jul 2023
CASE SHEET
28 Jul 2023
AIP - SUBMISSION COMMENTS FORM
11 Apr 2022
Show all 10 rows
CMP
29 Sept 2021
UPDATED CEMP
18 Mar 2021
UPDATED CONSTRUCTION MANAGEMENT PLAN
5 Mar 2021
UPDATED CONSTRUCTION MANAGEMENT PLAN
5 Mar 2021
UPDATED CONSTRUCTION MANAGEMENT PLAN
5 Mar 2021
UPDATED RISK ASSESSMENT METHOD STATEMENT
4 Mar 2021
UPDATED RISK ASSESSMENT METHOD STATEMENT
4 Mar 2021

Documents open on the Bexley portal (the portal needs its documents tab opened first — the link handles that). View the application page ↗

Decision

What happened?

Refused on 28 Jul 2023, delegated decision by Ian Smith — 133 weeks from submission (125 over the 8-week target).

Timeline

Date
Event
11 Jan 2021
Application received
8 Mar 2021
Statutory target date
28 Jul 2023
Delegated decision: Refused · Ian Smith
11 Jan 2021
Application received
8 Mar 2021
Statutory target date
28 Jul 2023
Delegated decision: Refused · Ian Smith

Public response

Measure
Count
Objections
0
In support
0
Total comments
0
Objections
0
In support
0
Total comments
0
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.