Planning application · Bexley

23/02231/FULM.

Units 8, 9, 13, 14 And 18 Mulberry Way Belvedere Kent DA17 6AN

Full / Other Planning at Units 8, 9, 13, 14 And 18 Mulberry Way Belvedere Kent DA17 6AN, received 11 Sep 2023 — withdrawn on 17 Dec 2025 (delegated, Ian Smith).

BexleyBELVEDEREDA17 6AN23/02231/FULM
ApprovedRefusedOther
At a glance · this applicationBexley profile →
Withdrawn
Outcome
17 Dec 2025
118 wks
Decision time
110 wks over the 8-week target
Conditions
not captured
58
Documents
58 linked
0
Objections
0 in support
No
Appeal
none recorded
Record from the Bexley planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Demolition of existing industrial and warehousing units and erection of a new unit (use classes E(g)(iii) B2 and B8) with ancillary office space and other associated works including creation of service yards, landscaping and boundary treatment, cycle and car parking.

Reference
23/02231/FULM
Type
Major Detailed Planning Application
Applicant
Agent / consultant
Case officer
Postcode
DA17 6AN
Council
Received
11 Sep 2023
Decision date
17 Dec 2025
Decision route
Delegated (officer)
Status
Withdrawn
Reference
23/02231/FULM
Type
Major Detailed Planning Application
Show all 14 rows
Applicant
Agent / consultant
Case officer
Postcode
DA17 6AN
Council
Received
11 Sep 2023
Decision date
17 Dec 2025
Decision route
Delegated (officer)
Status
Withdrawn
Documents

What was filed?

Document
Published
View
REVISED CYCLE PARKING
25 Feb 2025
FLOOD RISK ASSESSMENT/DRAINAGE STRATEGY
19 Feb 2025
RESPONSE TO HIGHWAYS FEEDBACK (REQUESTED S106 OBS)
11 Feb 2025
FLOOD RISK AND DRAINAGE STRATEGY PT 2
4 Feb 2025
FLOOD RISK & DRAINAGE STRATEGY - PT 1 (REDACTED)
4 Feb 2025
EGRESS PLAN
1 Nov 2024
RESPONSES TO LPA DRAINAGE COMMENTS
1 Nov 2024
PROPOSED DRAINAGE PLAN
1 Nov 2024
FLOOD ESTIMATION HANDBOOK INFORMATION (FEH)
1 Nov 2024
BNG METRIC
17 Oct 2024
REVISED CYCLE PARKING
25 Feb 2025
FLOOD RISK ASSESSMENT/DRAINAGE STRATEGY
19 Feb 2025
RESPONSE TO HIGHWAYS FEEDBACK (REQUESTED S106 OBS)
11 Feb 2025
Show all 10 rows
FLOOD RISK AND DRAINAGE STRATEGY PT 2
4 Feb 2025
FLOOD RISK & DRAINAGE STRATEGY - PT 1 (REDACTED)
4 Feb 2025
EGRESS PLAN
1 Nov 2024
RESPONSES TO LPA DRAINAGE COMMENTS
1 Nov 2024
PROPOSED DRAINAGE PLAN
1 Nov 2024
FLOOD ESTIMATION HANDBOOK INFORMATION (FEH)
1 Nov 2024
BNG METRIC
17 Oct 2024

Documents open on the Bexley portal (the portal needs its documents tab opened first — the link handles that). View the application page ↗

Decision

What happened?

Withdrawn on 17 Dec 2025, delegated decision by Ian Smith — 118 weeks from submission (110 over the 8-week target).

Timeline

Date
Event
11 Sep 2023
Application received
17 Dec 2025
Delegated decision: Withdrawn · Ian Smith
11 Sep 2023
Application received
17 Dec 2025
Delegated decision: Withdrawn · Ian Smith

Public response

Measure
Count
Objections
0
In support
0
Total comments
0
Objections
0
In support
0
Total comments
0
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.