Application
What is it?
Construction and operation of an Energy Storage System (BESS) for a temporary period of 40 years, including energy storage containers, transformers, inverters, switchgear, control building, internal access tracks, site access, earthworks, landscaping, and an underground cable connection route to Hurst Grid Substation, and associated infrastructure.
Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.
Other applications within 250 metres (context — nearby, not this application)
No other geocoded decision is recorded within 250 metres.