Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU

Full / Other Planning at Olympic Office Centre, 8 Fulton Road, Wembley, HA9 0NU, received 16 Feb 2023 — approved on 15 Mar 2024 by committee.

BrentWembley ParkHA9 0NU23/0578
ApprovedRefusedOther
At a glance · this applicationBrent profile →
Approved
Outcome
15 Mar 2024
56 wks
Decision time
48 wks over the 8-week target
Conditions
not captured
89
Documents
89 linked
1
Objections
0 in support
No
Appeal
none recorded
Record from the Brent planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Demolition of existing building and erection of building for use as a purpose-built Further Education College Campus with associated plant at roof level, provision of hard and soft landscaping and cycle parking facilities, loading bay and accessible parking bays on Rutherford Road frontage and drop off bay on Fulton Road, subject to Deed of Agreement dated 14th March 2024 under Section 106 of Town and Country Planning Act, 1990 as amended

Reference
23/0578
Type
Full Planning Permission
Agent / consultant
Case officer
Postcode
HA9 0NU
Council
Received
16 Feb 2023
Target date
18 Mar 2024
Decision date
15 Mar 2024
Decision route
Planning committee
Status
Decided
Reference
23/0578
Type
Full Planning Permission
Show all 15 rows
Agent / consultant
Case officer
Postcode
HA9 0NU
Council
Received
16 Feb 2023
Target date
18 Mar 2024
Decision date
15 Mar 2024
Decision route
Planning committee
Status
Decided
Documents

What was filed?

Document
Published
View
Redacted s106 agreement
18 Mar 2024
Post committee delegated report
15 Mar 2024
Final decision notice
15 Mar 2024
Final - supplementary report
11 Jul 2023
Final committee report
4 Jul 2023
Final committee report
4 Jul 2023
Flood risk assessment june 2023
29 Jun 2023
Drainage strategy june 2023
29 Jun 2023
Energy assessment may 2023
21 Jun 2023
Circular economy appendix ii to vi
21 Jun 2023
Redacted s106 agreement
18 Mar 2024
Post committee delegated report
15 Mar 2024
Final decision notice
15 Mar 2024
Show all 10 rows
Final - supplementary report
11 Jul 2023
Final committee report
4 Jul 2023
Final committee report
4 Jul 2023
Flood risk assessment june 2023
29 Jun 2023
Drainage strategy june 2023
29 Jun 2023
Energy assessment may 2023
21 Jun 2023
Circular economy appendix ii to vi
21 Jun 2023

Documents open on the Brent portal (the portal needs its documents tab opened first — the link handles that). View the application page ↗

Decision

What happened?

Approved on 15 Mar 2024, determined by the planning committee — 56 weeks from submission (48 over the 8-week target).

Timeline

Date
Event
16 Feb 2023
Application received
18 Mar 2024
Statutory target date
15 Mar 2024
Committee decision: Approved
16 Feb 2023
Application received
18 Mar 2024
Statutory target date
15 Mar 2024
Committee decision: Approved

Public response

Measure
Count
Objections
1
In support
0
Total comments
2
Objections
1
In support
0
Total comments
2
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Determined at committee
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Show all 4 rows
Determined at committee
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.