25/02228/HSE.

138 Harrington Road South Norwood London SE25 4NB

Householder at 138 Harrington Road South Norwood London SE25 4NB, received 3 Jul 2025 — approved on 26 Nov 2025 (delegated, Tiffany Liang).

CroydonWoodsideSE25 4NB25/02228/HSE
ApprovedRefusedOther
At a glance · this applicationCroydon profile →
Approved
Outcome
26 Nov 2025
21 wks
Decision time
13 wks over the 8-week target
Conditions
not captured
19
Documents
19 linked
0
Objections
0 in support
No
Appeal
none recorded
Record from the Croydon planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Increase in the ridge height of the main roof and construction of a dormer extension in the rear roof slope. Installation of two roof lights within the front roof slope

Reference
25/02228/HSE
Type
Householder Application
Agent / consultant
Case officer
Postcode
SE25 4NB
Council
Received
3 Jul 2025
Validated
25 Jul 2025
Target date
19 Sep 2025
Decision date
26 Nov 2025
Decision route
Delegated (officer)
Status
Decided
Reference
25/02228/HSE
Type
Householder Application
Show all 16 rows
Agent / consultant
Case officer
Postcode
SE25 4NB
Council
Received
3 Jul 2025
Validated
25 Jul 2025
Target date
19 Sep 2025
Decision date
26 Nov 2025
Decision route
Delegated (officer)
Status
Decided
Documents

What was filed?

Document
Published
View
GRANTED (PG) HOUSEHOLDER - DEC NOTICE
26 Nov 2025
OFFICER REPORT WEB - FINAL
26 Nov 2025
APPLICATION FORM - WITHOUT PERSONAL DATA
3 Jul 2025
ELEVATION (REAR) - EXISTING
3 Jul 2025
ELEVATION (FRONT) - EXISTING
3 Jul 2025
FLOOR PLAN
3 Jul 2025
FLOOR PLAN
3 Jul 2025
FLOOR PLAN
3 Jul 2025
ROOF PLAN - PROPOSED
3 Jul 2025
SECTION - PROPOSED
3 Jul 2025
GRANTED (PG) HOUSEHOLDER - DEC NOTICE
26 Nov 2025
OFFICER REPORT WEB - FINAL
26 Nov 2025
APPLICATION FORM - WITHOUT PERSONAL DATA
3 Jul 2025
Show all 10 rows
ELEVATION (REAR) - EXISTING
3 Jul 2025
ELEVATION (FRONT) - EXISTING
3 Jul 2025
FLOOR PLAN
3 Jul 2025
FLOOR PLAN
3 Jul 2025
FLOOR PLAN
3 Jul 2025
ROOF PLAN - PROPOSED
3 Jul 2025
SECTION - PROPOSED
3 Jul 2025

Documents open on the Croydon portal (the portal needs its documents tab opened first — the link handles that). View the application page ↗

Decision

What happened?

Approved on 26 Nov 2025, delegated decision by Tiffany Liang — 21 weeks from submission (13 over the 8-week target).

Timeline

Date
Event
3 Jul 2025
Application received
25 Jul 2025
Application validated
19 Sep 2025
Statutory target date
26 Nov 2025
Delegated decision: Approved · Tiffany Liang
3 Jul 2025
Application received
25 Jul 2025
Application validated
19 Sep 2025
Statutory target date
Show all 4 rows
26 Nov 2025
Delegated decision: Approved · Tiffany Liang

Public response

Measure
Count
Objections
0
In support
0
Total comments
0
Objections
0
In support
0
Total comments
0
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.