216215FUL.

13-15 The Green Southall Middlesex UB2 4AH

Full / Other Planning at 13-15 The Green Southall Middlesex UB2 4AH, received 21 Oct 2021 — approved on 16 Feb 2024 by committee.

EalingNorwood GreenUB2 4AH216215FUL
ApprovedRefusedOther
At a glance · this applicationEaling profile →
Approved
Outcome
16 Feb 2024
121 wks
Decision time
113 wks over the 8-week target
Conditions
not captured
113
Documents
113 linked
3
Objections
0 in support
No
Appeal
none recorded
Record from the Ealing planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Demolition of the existing buildings and construction of a part 23 storey, part 19 storey and part 14 storey building to provide 95 residential units, including the creation of a basement level, incorporating flexible amenity space, cycle parking, refuse storage and public realm improvements and landscaping

Reference
216215FUL
Type
Full Application
Agent / consultant
Case officer
Postcode
UB2 4AH
Council
Received
21 Oct 2021
Target date
20 Jan 2022
Decision date
16 Feb 2024
Decision route
Planning committee
Status
Granted with S106 conditions
Reference
216215FUL
Type
Full Application
Show all 15 rows
Agent / consultant
Case officer
Postcode
UB2 4AH
Council
Received
21 Oct 2021
Target date
20 Jan 2022
Decision date
16 Feb 2024
Decision route
Planning committee
Status
Granted with S106 conditions
Documents

What was filed?

Document
Published
View
FINAL DECISION NOTICE
16 Feb 2024
LEGAL AGREEMENT
16 Feb 2024
REVISED FIRE STATEMENT REV 05
19 Dec 2023
ENERGY BE LEAN STATEMENT
22 Oct 2023
ENERGY BE GREEN STATEMENT
22 Oct 2023
DWEELLING EMISSIONS SAP REPORT FLOOR 12
22 Oct 2023
DWEELLING EMISSIONS SAP REPORT FLOOR 12 -2
22 Oct 2023
DWELLING EMISSIONS SAP REPORT FLOOR 12 -3
22 Oct 2023
DWELLING EMISSIONS SAP REPORT FLOOR 12 -4
22 Oct 2023
DWELLING EMISSIONS SAP REPORT FLOOR 21 -1
22 Oct 2023
FINAL DECISION NOTICE
16 Feb 2024
LEGAL AGREEMENT
16 Feb 2024
REVISED FIRE STATEMENT REV 05
19 Dec 2023
Show all 10 rows
ENERGY BE LEAN STATEMENT
22 Oct 2023
ENERGY BE GREEN STATEMENT
22 Oct 2023
DWEELLING EMISSIONS SAP REPORT FLOOR 12
22 Oct 2023
DWEELLING EMISSIONS SAP REPORT FLOOR 12 -2
22 Oct 2023
DWELLING EMISSIONS SAP REPORT FLOOR 12 -3
22 Oct 2023
DWELLING EMISSIONS SAP REPORT FLOOR 12 -4
22 Oct 2023
DWELLING EMISSIONS SAP REPORT FLOOR 21 -1
22 Oct 2023

Documents open on the Ealing portal (the portal needs its documents tab opened first — the link handles that). View the application page ↗

Decision

What happened?

Approved on 16 Feb 2024, determined by the planning committee — 121 weeks from submission (113 over the 8-week target).

Timeline

Date
Event
21 Oct 2021
Application received
20 Jan 2022
Statutory target date
16 Feb 2024
Committee decision: Approved
21 Oct 2021
Application received
20 Jan 2022
Statutory target date
16 Feb 2024
Committee decision: Approved

Public response

Measure
Count
Objections
3
In support
0
Total comments
3
Objections
3
In support
0
Total comments
3
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Determined at committee
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Show all 4 rows
Determined at committee
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)