Planning application · Hackney

2004/0546.

Flat Iron, 77 Curtain Road, Hackney, London, EC2A 3BS

Full / Other Planning at Flat Iron, 77 Curtain Road, Hackney, London, EC2A 3BS, received 9 Mar 2004 — approved on 18 May 2006 by committee.

ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
18 May 2006
114 wks
Decision time
106 wks over the 8-week target
Conditions
not captured
6
Documents
6 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Erection of 7 storey building plus basement to provide retail A1 use (554 sqm), 9 live/work units (666 sqm) at 1st, 2nd and 3rd floor level and 6 residential units (628 sqm) at 4th, 5th and 6th level comprising 3 x 2 bed and 3 x 4 bed units, including enclosed bicycle parking facilities and refuse/r

Reference
2004/0546
Type
Full Planning Permission
Agent / consultant
Case officer
Postcode
Council
Received
9 Mar 2004
Validated
7 Apr 2004
Target date
2 Jun 2004
Decision date
18 May 2006
Decision route
Planning committee
Status
Final Decision
Reference
2004/0546
Type
Full Planning Permission
Show all 17 rows
Agent / consultant
Case officer
Postcode
Council
Received
9 Mar 2004
Validated
7 Apr 2004
Target date
2 Jun 2004
Decision date
18 May 2006
Decision route
Planning committee
Status
Final Decision
Documents

What was filed?

Document
Published
View
2004/0546 Planning -
2004/0546 Planning -
2004/0546 Planning -
2004/0546 Planning -
2004/0546 Planning -
2004/0546 Planning -
2004/0546 Planning -
2004/0546 Planning -
2004/0546 Planning -
Show all 6 rows
2004/0546 Planning -
2004/0546 Planning -
2004/0546 Planning -

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 18 May 2006, determined by the planning committee — 114 weeks from submission (106 over the 8-week target).

Timeline

Date
Event
9 Mar 2004
Application received
7 Apr 2004
Application validated
2 Jun 2004
Statutory target date
18 May 2006
Committee decision: Approved
9 Mar 2004
Application received
7 Apr 2004
Application validated
2 Jun 2004
Statutory target date
Show all 4 rows
18 May 2006
Committee decision: Approved

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Determined at committee
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Show all 4 rows
Determined at committee
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.