2021/0706.
WATER WORKS REAR OF THE CASTLE CLIMBING CENTRE Green Lanes, Hackney
Full / Other Planning at WATER WORKS REAR OF THE CASTLE CLIMBING CENTRE Green Lanes, Hackney, received 3 Mar 2021 — approved on 28 Apr 2021 (delegated, Gerard Livett).
What is it?
Installation of booster pump facility until August 2021 (part retrospective)
Show all 14 rows
What was filed?
Documents open on the Hackney portal. View the application page ↗
What happened?
Approved on 28 Apr 2021, delegated decision by Gerard Livett — 8 weeks from submission.
Timeline
Public response
Comment counts were not captured for this application.
Who is involved?
What affects it?
Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.
Other applications within 250 metres (context — nearby, not this application)
No other geocoded decision is recorded within 250 metres.