Full / Other Planning at Jack Watts Community Flat, 10 Detmold Road, Hackney, London, E5 9NJ, received 24 Oct 2022 — approved on 26 Jul 2023 by committee.

HackneyLea Bridge WardE5 9NJ2022/2563
ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
26 Jul 2023
39 wks
Decision time
31 wks over the 8-week target
Conditions
not captured
11
Documents
11 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Conversion of ground floor community meeting rooms (class F2 b) to a 1 bedroom residential unit (class C3)

Reference
2022/2563
Type
Full Planning Permission
Applicant
Agent / consultant
Case officer
Postcode
E5 9NJ
Council
Received
24 Oct 2022
Validated
16 Nov 2022
Target date
26 Jul 2023
Decision date
26 Jul 2023
Decision route
Planning committee
Status
Final Decision
Reference
2022/2563
Type
Full Planning Permission
Show all 16 rows
Applicant
Agent / consultant
Case officer
Postcode
E5 9NJ
Council
Received
24 Oct 2022
Validated
16 Nov 2022
Target date
26 Jul 2023
Decision date
26 Jul 2023
Decision route
Planning committee
Status
Final Decision
Documents

What was filed?

Document
Published
View
Completed-S106-10-Detmold-Rd-dated-25_07_2307251614
28 Jul 2023
DN-Full Planning Granted Final
26 Jul 2023
Officer Report
26 Jul 2023
Community Infrastructure Levy - Completed form
26 Oct 2022
Planning statement
26 Oct 2022
Design and access statement
26 Oct 2022
SBD Secure Cycle Protection Box
26 Oct 2022
Proposed Floor plan
26 Oct 2022
Floor Plan - Existing
26 Oct 2022
Block plan of the site
26 Oct 2022
Completed-S106-10-Detmold-Rd-dated-25_07_2307251614
28 Jul 2023
DN-Full Planning Granted Final
26 Jul 2023
Officer Report
26 Jul 2023
Show all 10 rows
Community Infrastructure Levy - Completed form
26 Oct 2022
Planning statement
26 Oct 2022
Design and access statement
26 Oct 2022
SBD Secure Cycle Protection Box
26 Oct 2022
Proposed Floor plan
26 Oct 2022
Floor Plan - Existing
26 Oct 2022
Block plan of the site
26 Oct 2022

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 26 Jul 2023, determined by the planning committee — 39 weeks from submission (31 over the 8-week target).

Timeline

Date
Event
24 Oct 2022
Application received
16 Nov 2022
Application validated
26 Jul 2023
Statutory target date
26 Jul 2023
Committee decision: Approved
24 Oct 2022
Application received
16 Nov 2022
Application validated
26 Jul 2023
Statutory target date
Show all 4 rows
26 Jul 2023
Committee decision: Approved

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Determined at committee
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Show all 4 rows
Determined at committee
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.