Planning Atlas
Planning AtlasHackneyDe Beauvoir Ward wardN1 4HN90 Culford Road, Hackney, London, N1 4HN2022/3049
Planning application · Hackney

2022/3049.

90 Culford Road, Hackney, London, N1 4HN

Householder at 90 Culford Road, Hackney, London, N1 4HN, received 19 Dec 2022 — approved on 17 Mar 2023 (delegated, Micheal Garvey).

ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
17 Mar 2023
13 wks
Decision time
5 wks over the 8-week target
Conditions
not captured
20
Documents
20 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Erection of single storey side and rear extension at lower ground floor, replace upper ground floor rear window with new window and installation of PV panels to main roof.

Reference
2022/3049
Type
Householder Planning
Agent / consultant
Case officer
Postcode
Council
Received
19 Dec 2022
Target date
17 Mar 2023
Decision date
17 Mar 2023
Decision route
Delegated (officer)
Status
Final Decision
Reference
2022/3049
Type
Householder Planning
Show all 16 rows
Agent / consultant
Case officer
Postcode
Council
Received
19 Dec 2022
Target date
17 Mar 2023
Decision date
17 Mar 2023
Decision route
Delegated (officer)
Status
Final Decision
Documents

What was filed?

Document
Published
View
Officer Report
17 Mar 2023
DN-Householder Granted Final
17 Mar 2023
Amended proposed sections/floor plans
16 Mar 2023
Community Infrastructure Levy - Completed form
20 Dec 2022
Design and access statement
20 Dec 2022
Sections As Proposed PL-06
20 Dec 2022
Sections 1-1 & 2-2 As Proposed PL-05
20 Dec 2022
Front & Rear Elevations as Proposed PL04
20 Dec 2022
First Floor & Roof Plan As Proposed PL-03
20 Dec 2022
Upper Ground Floor Plan As Proposed PL02
20 Dec 2022
Officer Report
17 Mar 2023
DN-Householder Granted Final
17 Mar 2023
Amended proposed sections/floor plans
16 Mar 2023
Show all 10 rows
Community Infrastructure Levy - Completed form
20 Dec 2022
Design and access statement
20 Dec 2022
Sections As Proposed PL-06
20 Dec 2022
Sections 1-1 & 2-2 As Proposed PL-05
20 Dec 2022
Front & Rear Elevations as Proposed PL04
20 Dec 2022
First Floor & Roof Plan As Proposed PL-03
20 Dec 2022
Upper Ground Floor Plan As Proposed PL02
20 Dec 2022

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 17 Mar 2023, delegated decision by Micheal Garvey — 13 weeks from submission (5 over the 8-week target).

Timeline

Date
Event
19 Dec 2022
Application received
17 Mar 2023
Statutory target date
17 Mar 2023
Delegated decision: Approved · Micheal Garvey
19 Dec 2022
Application received
17 Mar 2023
Statutory target date
17 Mar 2023
Delegated decision: Approved · Micheal Garvey

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.