Planning Atlas
Planning AtlasHackneyLea Bridge Ward wardE5 0EX60 Rushmore Road, Hackney, London, E5 0EX2023/0889
Planning application · Hackney

2023/0889.

60 Rushmore Road, Hackney, London, E5 0EX

Lawful Development Certificate at 60 Rushmore Road, Hackney, London, E5 0EX, received 19 Apr 2023 — refused on 30 Jun 2023 (delegated, Jessica Neeve).

ApprovedRefusedOther
At a glance · this applicationHackney profile →
Refused
Outcome
30 Jun 2023
10 wks
Decision time
2 wks over the 8-week target
Conditions
not captured
18
Documents
18 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Proposed works: Erection of a rear roof extension over the outrigger; the erection of a rear roof extension over the original dwelling house; and the erection of an outbuilding.

Reference
2023/0889
Type
Certificate of Lawful Development Existing/Proposed
Agent / consultant
Case officer
Postcode
Council
Received
19 Apr 2023
Validated
5 May 2023
Target date
30 Jun 2023
Decision date
30 Jun 2023
Decision route
Delegated (officer)
Status
Final Decision
Reference
2023/0889
Type
Certificate of Lawful Development Existing/Proposed
Show all 17 rows
Agent / consultant
Case officer
Postcode
Council
Received
19 Apr 2023
Validated
5 May 2023
Target date
30 Jun 2023
Decision date
30 Jun 2023
Decision route
Delegated (officer)
Status
Final Decision
Documents

What was filed?

Document
Published
View
DN-Lawful Development Certificate Refusal Final
30 Jun 2023
Officer Report
29 Jun 2023
Existing ground floor site plan
5 May 2023
Existing rear/south elevation
5 May 2023
Existing front/north elevation
5 May 2023
Existing roof level site plan
5 May 2023
Existing side/west elevation
5 May 2023
Existing side/east elevation
5 May 2023
Proposed second floor plan
5 May 2023
Proposed ground floor site plan
5 May 2023
DN-Lawful Development Certificate Refusal Final
30 Jun 2023
Officer Report
29 Jun 2023
Existing ground floor site plan
5 May 2023
Show all 10 rows
Existing rear/south elevation
5 May 2023
Existing front/north elevation
5 May 2023
Existing roof level site plan
5 May 2023
Existing side/west elevation
5 May 2023
Existing side/east elevation
5 May 2023
Proposed second floor plan
5 May 2023
Proposed ground floor site plan
5 May 2023

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Refused on 30 Jun 2023, delegated decision by Jessica Neeve — 10 weeks from submission (2 over the 8-week target).

Timeline

Date
Event
19 Apr 2023
Application received
5 May 2023
Application validated
30 Jun 2023
Statutory target date
30 Jun 2023
Delegated decision: Refused · Jessica Neeve
19 Apr 2023
Application received
5 May 2023
Application validated
30 Jun 2023
Statutory target date
Show all 4 rows
30 Jun 2023
Delegated decision: Refused · Jessica Neeve

Why it was refused

Reason
As stated on the decision notice
1
This Certificate is issued solely for the purpose of Section 191 of the Town and Country Planning Act 1990 (as amended).
2
It certifies that the use/ operations/ matter specified in the First Schedule taking place on the land described in the Second Schedule would have been lawful on the specified date and, thus was not liable to enforcement action under Section 172 of the 1990 Act on that date.
3
This Certificate applies only to the extent of the use/ operations/ matter described in the First Schedule and to the land specified in the Second Schedule. Any use/ operations/ matter which is materially different from that described or which relates to other land may render the owner or occupier liable to enforcement action.
4
The effect of the certificate is also qualified by the proviso in Section 192(4) of the 1990 Act (as amended) which states that the lawfulness of a described use or operation is only conclusively presumed where there has been no material change, before the use is instituted or the operations begun, in any of the matters relevant to determine such lawfulness. Date of Decision: 30-06-2023
1
This Certificate is issued solely for the purpose of Section 191 of the Town and Country Planning Act 1990 (as amended).
2
It certifies that the use/ operations/ matter specified in the First Schedule taking place on the land described in the Second Schedule would have been lawful on the specified date and, thus was not liable to enforcement action under Section 172 of the 1990 Act on that date.
3
This Certificate applies only to the extent of the use/ operations/ matter described in the First Schedule and to the land specified in the Second Schedule. Any use/ operations/ matter which is materially different from that described or which relates to other land may render the owner or occupier liable to enforcement action.
Show all 4 rows
4
The effect of the certificate is also qualified by the proviso in Section 192(4) of the 1990 Act (as amended) which states that the lawfulness of a described use or operation is only conclusively presumed where there has been no material change, before the use is instituted or the operations begun, in any of the matters relevant to determine such lawfulness. Date of Decision: 30-06-2023

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.