Householder at 2 Fassett Square, Hackney, London, E8 1DQ, received 31 Jul 2024 — approved on 20 Feb 2025 (delegated, Britney Ford).

HackneyDalston WardE8 1DQ2024/1644
ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
20 Feb 2025
29 wks
Decision time
21 wks over the 8-week target
Conditions
not captured
10
Documents
10 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Installation of external wall insulation in white render finish to rear walls; the replacement of existing single glazed timber framed windows with double glazed timber framed windows; and the replacement of existing timber doors with uPVC doors.

Reference
2024/1644
Type
Householder Planning
Case officer
Postcode
Council
Received
31 Jul 2024
Validated
1 Aug 2024
Target date
21 Feb 2025
Decision date
20 Feb 2025
Decision route
Delegated (officer)
Status
Final Decision
Reference
2024/1644
Type
Householder Planning
Show all 17 rows
Case officer
Postcode
Council
Received
31 Jul 2024
Validated
1 Aug 2024
Target date
21 Feb 2025
Decision date
20 Feb 2025
Decision route
Delegated (officer)
Status
Final Decision
Documents

What was filed?

Document
Published
View
DN-Householder Granted Final
20 Feb 2025
Officer Report
30 Jan 2025
Community Infrastructure Levy - Completed form
1 Aug 2024
Design and access statement
1 Aug 2024
Street Scene/Context Plan - Proposed
1 Aug 2024
Mixed/Combined Plans
1 Aug 2024
Block plan of the site
1 Aug 2024
The location plan
1 Aug 2024
A summary of the attachments in the proposal
1 Aug 2024
Application Form - Without Personal Data
1 Aug 2024
DN-Householder Granted Final
20 Feb 2025
Officer Report
30 Jan 2025
Community Infrastructure Levy - Completed form
1 Aug 2024
Show all 10 rows
Design and access statement
1 Aug 2024
Street Scene/Context Plan - Proposed
1 Aug 2024
Mixed/Combined Plans
1 Aug 2024
Block plan of the site
1 Aug 2024
The location plan
1 Aug 2024
A summary of the attachments in the proposal
1 Aug 2024
Application Form - Without Personal Data
1 Aug 2024

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 20 Feb 2025, delegated decision by Britney Ford — 29 weeks from submission (21 over the 8-week target).

Timeline

Date
Event
31 Jul 2024
Application received
1 Aug 2024
Application validated
21 Feb 2025
Statutory target date
20 Feb 2025
Delegated decision: Approved · Britney Ford
31 Jul 2024
Application received
1 Aug 2024
Application validated
21 Feb 2025
Statutory target date
Show all 4 rows
20 Feb 2025
Delegated decision: Approved · Britney Ford

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.