Householder at 58 Middleton Road, Hackney, London, E8 4BS, received 20 Aug 2024 — approved on 19 Dec 2024 (delegated, Sam Dargue).

ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
19 Dec 2024
17 wks
Decision time
9 wks over the 8-week target
Conditions
not captured
12
Documents
12 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Erection of a raised black painted metal terrace, to match existing adjacent metal railings, protruding from the rear façade, at upper ground level and extension of the brick party fence wall vertically by 2m, in-line with the proposed metal terrace, in London stock brick to match existing building

Reference
2024/1804
Type
Householder Planning
Agent / consultant
Case officer
Postcode
Council
Received
20 Aug 2024
Target date
20 Dec 2024
Decision date
19 Dec 2024
Decision route
Delegated (officer)
Status
Final Decision
Reference
2024/1804
Type
Householder Planning
Show all 16 rows
Agent / consultant
Case officer
Postcode
Council
Received
20 Aug 2024
Target date
20 Dec 2024
Decision date
19 Dec 2024
Decision route
Delegated (officer)
Status
Final Decision
Documents

What was filed?

Document
Published
View
DN-Householder Granted Final
19 Dec 2024
Officer Report
12 Dec 2024
PROPOSED DRAWINGS
21 Aug 2024
Projection - Existing
21 Aug 2024
EXISTING BLOCK PLAN
21 Aug 2024
Community Infrastructure Levy - Completed form
21 Aug 2024
Design and access statement
21 Aug 2024
Mixed/Combined Plans
21 Aug 2024
Mixed/Combined Plans
21 Aug 2024
The location plan
21 Aug 2024
DN-Householder Granted Final
19 Dec 2024
Officer Report
12 Dec 2024
PROPOSED DRAWINGS
21 Aug 2024
Show all 10 rows
Projection - Existing
21 Aug 2024
EXISTING BLOCK PLAN
21 Aug 2024
Community Infrastructure Levy - Completed form
21 Aug 2024
Design and access statement
21 Aug 2024
Mixed/Combined Plans
21 Aug 2024
Mixed/Combined Plans
21 Aug 2024
The location plan
21 Aug 2024

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 19 Dec 2024, delegated decision by Sam Dargue — 17 weeks from submission (9 over the 8-week target).

Timeline

Date
Event
20 Aug 2024
Application received
20 Dec 2024
Statutory target date
19 Dec 2024
Delegated decision: Approved · Sam Dargue
20 Aug 2024
Application received
20 Dec 2024
Statutory target date
19 Dec 2024
Delegated decision: Approved · Sam Dargue

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.