Householder at 167 Middleton Road, Hackney, London, E8 4LL, received 27 Sep 2024 — approved on 26 Feb 2025 (delegated, Lorraine Murphy).

ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
26 Feb 2025
22 wks
Decision time
14 wks over the 8-week target
Conditions
not captured
16
Documents
16 linked
0
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Erection of rear dormer together with the installation of roof lights on the front, side, rear outrigger roof slopes as well as the the erection of the single storey rear extension, the construction of a light well to the rear of the dwelling with traditional railings and enlargement of the basement

Reference
2024/2094
Type
Householder Planning
Agent / consultant
Case officer
Postcode
Council
Received
27 Sep 2024
Validated
17 Dec 2024
Target date
28 Feb 2025
Decision date
26 Feb 2025
Decision route
Delegated (officer)
Status
Final Decision
Reference
2024/2094
Type
Householder Planning
Show all 17 rows
Agent / consultant
Case officer
Postcode
Council
Received
27 Sep 2024
Validated
17 Dec 2024
Target date
28 Feb 2025
Decision date
26 Feb 2025
Decision route
Delegated (officer)
Status
Final Decision
Documents

What was filed?

Document
Published
View
DN-Householder Granted Final
26 Feb 2025
Officer Report
26 Feb 2025
revised plans
25 Feb 2025
revised existing and proposed
6 Feb 2025
Updated Design and Access Statemen
13 Jan 2025
Sections-Elevations-Ammended
13 Dec 2024
Plans-Sections-Elavation-Planning-ammendment
14 Nov 2024
Mixed/Combined Plans
30 Sept 2024
Community Infrastructure Levy - Completed form
30 Sept 2024
Block plan of the site
30 Sept 2024
DN-Householder Granted Final
26 Feb 2025
Officer Report
26 Feb 2025
revised plans
25 Feb 2025
Show all 10 rows
revised existing and proposed
6 Feb 2025
Updated Design and Access Statemen
13 Jan 2025
Sections-Elevations-Ammended
13 Dec 2024
Plans-Sections-Elavation-Planning-ammendment
14 Nov 2024
Mixed/Combined Plans
30 Sept 2024
Community Infrastructure Levy - Completed form
30 Sept 2024
Block plan of the site
30 Sept 2024

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 26 Feb 2025, delegated decision by Lorraine Murphy — 22 weeks from submission (14 over the 8-week target).

Timeline

Date
Event
27 Sep 2024
Application received
17 Dec 2024
Application validated
28 Feb 2025
Statutory target date
26 Feb 2025
Delegated decision: Approved · Lorraine Murphy
27 Sep 2024
Application received
17 Dec 2024
Application validated
28 Feb 2025
Statutory target date
Show all 4 rows
26 Feb 2025
Delegated decision: Approved · Lorraine Murphy

Public response

Measure
Count
Objections
0
Objections
0
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.