Full / Other Planning at 55 - 59 Rivington Street, Hackney, London, EC2A 3QB, received 3 Apr 2025 — approved on 9 Jul 2025 (delegated, Lasse Lottgen).

ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
9 Jul 2025
14 wks
Decision time
6 wks over the 8-week target
Conditions
not captured
11
Documents
11 linked
0
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Replacement of stairwell glazed panel with solid insulated wall

Reference
2025/0792
Type
Full Planning Permission
Applicant
Agent / consultant
Case officer
Postcode
Council
Received
3 Apr 2025
Validated
14 May 2025
Target date
9 Jul 2025
Decision date
9 Jul 2025
Decision route
Delegated (officer)
Status
Final Decision
Reference
2025/0792
Type
Full Planning Permission
Show all 16 rows
Applicant
Agent / consultant
Case officer
Postcode
Council
Received
3 Apr 2025
Validated
14 May 2025
Target date
9 Jul 2025
Decision date
9 Jul 2025
Decision route
Delegated (officer)
Status
Final Decision
Documents

What was filed?

Document
Published
View
DN-Full Planning Granted Final
9 Jul 2025
Officer Report
9 Jul 2025
2nd FLOOR PLANS.pdf
3 Apr 2025
PHOTOMONTAGE.pdf
3 Apr 2025
FIRE SAFETY STATEMENT.pdf
3 Apr 2025
CIL COMPLETED.pdf
3 Apr 2025
design statement.pdf
3 Apr 2025
25-03-01-03 COURTYARD ELEVATION B-B.pdf
3 Apr 2025
25-03-01-02 COURTYARD ELEVATION A-A.pdf
3 Apr 2025
LocationPlan.pdf
3 Apr 2025
DN-Full Planning Granted Final
9 Jul 2025
Officer Report
9 Jul 2025
2nd FLOOR PLANS.pdf
3 Apr 2025
Show all 10 rows
PHOTOMONTAGE.pdf
3 Apr 2025
FIRE SAFETY STATEMENT.pdf
3 Apr 2025
CIL COMPLETED.pdf
3 Apr 2025
design statement.pdf
3 Apr 2025
25-03-01-03 COURTYARD ELEVATION B-B.pdf
3 Apr 2025
25-03-01-02 COURTYARD ELEVATION A-A.pdf
3 Apr 2025
LocationPlan.pdf
3 Apr 2025

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 9 Jul 2025, delegated decision by Lasse Lottgen — 14 weeks from submission (6 over the 8-week target).

Timeline

Date
Event
3 Apr 2025
Application received
14 May 2025
Application validated
9 Jul 2025
Statutory target date
9 Jul 2025
Delegated decision: Approved · Lasse Lottgen
3 Apr 2025
Application received
14 May 2025
Application validated
9 Jul 2025
Statutory target date
Show all 4 rows
9 Jul 2025
Delegated decision: Approved · Lasse Lottgen

Public response

Measure
Count
Objections
0
Objections
0
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.