Princess Of Wales, 146 Lea Bridge Road, Hackney, London, E5 9RB

Full / Other Planning at Princess Of Wales, 146 Lea Bridge Road, Hackney, London, E5 9RB, received 23 Apr 2025 — approved on 19 Mar 2026 (delegated, Bronte Donato).

HackneyLea Bridge WardE5 9RB2025/0960
ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
19 Mar 2026
47 wks
Decision time
39 wks over the 8-week target
Conditions
not captured
21
Documents
21 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Erection of a New Retractable Awning Structure within the Existing Beer Garden & Redecoration Works to the Existing Pub Building.

Reference
2025/0960
Type
Full Planning Permission
Applicant
Agent / consultant
Case officer
Postcode
E5 9RB
Council
Received
23 Apr 2025
Validated
17 Jun 2025
Target date
19 Mar 2026
Decision date
19 Mar 2026
Decision route
Delegated (officer)
Status
Final Decision
Reference
2025/0960
Type
Full Planning Permission
Show all 16 rows
Applicant
Agent / consultant
Case officer
Postcode
E5 9RB
Council
Received
23 Apr 2025
Validated
17 Jun 2025
Target date
19 Mar 2026
Decision date
19 Mar 2026
Decision route
Delegated (officer)
Status
Final Decision
Documents

What was filed?

Document
Published
View
DN-Full Planning Granted Final
19 Mar 2026
Revised Noise Report
19 Mar 2026
Noise Assessment
17 Mar 2026
Officer Report
13 Jan 2026
Arboricultural Implication Study
13 Jan 2026
Tree Survey
13 Jan 2026
Flood risk assessment
24 Apr 2025
Fire Statement
24 Apr 2025
Proposed GF Plan.pdf
24 Apr 2025
Proposed Roof Plan.pdf
24 Apr 2025
DN-Full Planning Granted Final
19 Mar 2026
Revised Noise Report
19 Mar 2026
Noise Assessment
17 Mar 2026
Show all 10 rows
Officer Report
13 Jan 2026
Arboricultural Implication Study
13 Jan 2026
Tree Survey
13 Jan 2026
Flood risk assessment
24 Apr 2025
Fire Statement
24 Apr 2025
Proposed GF Plan.pdf
24 Apr 2025
Proposed Roof Plan.pdf
24 Apr 2025

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 19 Mar 2026, delegated decision by Bronte Donato — 47 weeks from submission (39 over the 8-week target).

Timeline

Date
Event
23 Apr 2025
Application received
17 Jun 2025
Application validated
19 Mar 2026
Statutory target date
19 Mar 2026
Delegated decision: Approved · Bronte Donato
23 Apr 2025
Application received
17 Jun 2025
Application validated
19 Mar 2026
Statutory target date
Show all 4 rows
19 Mar 2026
Delegated decision: Approved · Bronte Donato

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.