Full / Other Planning at Next Move, 63 - 65 Stoke Newington Church Street, Hackney, London, N16 0AR, received 19 Jun 2025 — approved on 9 Mar 2026 (delegated, Lorraine Murphy).

HackneyStoke Newington WardN16 0AR2025/1414
ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
9 Mar 2026
38 wks
Decision time
30 wks over the 8-week target
Conditions
not captured
11
Documents
11 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Division of an existing Class E unit to create a new, separate Class E unit and alterations to the current shopfront, including the installation of a new door and a new shop window.

Reference
2025/1414
Type
Full Planning Permission
Case officer
Postcode
N16 0AR
Council
Received
19 Jun 2025
Validated
12 Jan 2026
Target date
9 Mar 2026
Decision date
9 Mar 2026
Decision route
Delegated (officer)
Status
Final Decision
Reference
2025/1414
Type
Full Planning Permission
Show all 16 rows
Case officer
Postcode
N16 0AR
Council
Received
19 Jun 2025
Validated
12 Jan 2026
Target date
9 Mar 2026
Decision date
9 Mar 2026
Decision route
Delegated (officer)
Status
Final Decision
Documents

What was filed?

Document
Published
View
DN-Full Planning Granted Final
9 Mar 2026
Officer Report
9 Mar 2026
Design-and-Access-Statement
12 Jan 2026
Plan-and-Elevation-as-Existing
12 Jan 2026
Plan-and-Elevation-as-Proposed
12 Jan 2026
Community Infrastructure Levy
20 Jun 2025
Design and Access Statement.pdf
20 Jun 2025
Proposed Elevation
20 Jun 2025
Existing Elevation
20 Jun 2025
LocationPlan.pdf
20 Jun 2025
DN-Full Planning Granted Final
9 Mar 2026
Officer Report
9 Mar 2026
Design-and-Access-Statement
12 Jan 2026
Show all 10 rows
Plan-and-Elevation-as-Existing
12 Jan 2026
Plan-and-Elevation-as-Proposed
12 Jan 2026
Community Infrastructure Levy
20 Jun 2025
Design and Access Statement.pdf
20 Jun 2025
Proposed Elevation
20 Jun 2025
Existing Elevation
20 Jun 2025
LocationPlan.pdf
20 Jun 2025

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 9 Mar 2026, delegated decision by Lorraine Murphy — 38 weeks from submission (30 over the 8-week target).

Timeline

Date
Event
19 Jun 2025
Application received
12 Jan 2026
Application validated
9 Mar 2026
Statutory target date
9 Mar 2026
Delegated decision: Approved · Lorraine Murphy
19 Jun 2025
Application received
12 Jan 2026
Application validated
9 Mar 2026
Statutory target date
Show all 4 rows
9 Mar 2026
Delegated decision: Approved · Lorraine Murphy

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.