Planning Atlas
Planning AtlasHackneyCazenove Ward ward2025/2102
Planning application · Hackney

2025/2102.

1 Clapton Terrace, Hackney, London, E5 9BW

Full / Other Planning at 1 Clapton Terrace, Hackney, London, E5 9BW, received 22 Sep 2025 — approved on 14 May 2026 (delegated, Danny Huber).

HackneyCazenove WardE5 9BW2025/2102
ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
14 May 2026
33 wks
Decision time
25 wks over the 8-week target
Conditions
not captured
30
Documents
30 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Installation of solar photovoltaic panels and associated safe access systems to the roofs of the church and Common Rooms at St Thomas Clapton Common.

Reference
2025/2102
Type
Full Planning Permission
Agent / consultant
Case officer
Postcode
E5 9BW
Council
Received
22 Sep 2025
Target date
14 May 2026
Decision date
14 May 2026
Decision route
Delegated (officer)
Status
Final Decision
Reference
2025/2102
Type
Full Planning Permission
Show all 15 rows
Agent / consultant
Case officer
Postcode
E5 9BW
Council
Received
22 Sep 2025
Target date
14 May 2026
Decision date
14 May 2026
Decision route
Delegated (officer)
Status
Final Decision
Documents

What was filed?

Document
Published
View
STC-PL-221A-PROPOSED-SECTION-A-WEST-PL-02
10 Feb 2026
STC-PL-233-PROPOSED-WEST-ELEVATION-PL-02
10 Feb 2026
Pages-from-02-keeline-ii-instructions-for-use-manual-05-02-2
10 Feb 2026
STC-PL-551-Typical-Fall-Arrest-Bracket-PL01
10 Feb 2026
Design and access statement
23 Sept 2025
PROPOSED SECTION A - WEST_PL-01.pdf
23 Sept 2025
PROPOSED WEST ELEVATION_PL-01.pdf
23 Sept 2025
PROPOSED SOUTH ELEVATION - EAST_PL-01.pdf
23 Sept 2025
PROPOSED SECTION B - EAST_PL-01.pdf
23 Sept 2025
PROPOSED SECTION A - EAST_PL-01.pdf
23 Sept 2025
STC-PL-221A-PROPOSED-SECTION-A-WEST-PL-02
10 Feb 2026
STC-PL-233-PROPOSED-WEST-ELEVATION-PL-02
10 Feb 2026
Pages-from-02-keeline-ii-instructions-for-use-manual-05-02-2
10 Feb 2026
Show all 10 rows
STC-PL-551-Typical-Fall-Arrest-Bracket-PL01
10 Feb 2026
Design and access statement
23 Sept 2025
PROPOSED SECTION A - WEST_PL-01.pdf
23 Sept 2025
PROPOSED WEST ELEVATION_PL-01.pdf
23 Sept 2025
PROPOSED SOUTH ELEVATION - EAST_PL-01.pdf
23 Sept 2025
PROPOSED SECTION B - EAST_PL-01.pdf
23 Sept 2025
PROPOSED SECTION A - EAST_PL-01.pdf
23 Sept 2025

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 14 May 2026, delegated decision by Danny Huber — 33 weeks from submission (25 over the 8-week target).

Timeline

Date
Event
22 Sep 2025
Application received
14 May 2026
Statutory target date
14 May 2026
Delegated decision: Approved · Danny Huber
22 Sep 2025
Application received
14 May 2026
Statutory target date
14 May 2026
Delegated decision: Approved · Danny Huber

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.