Full / Other Planning at SAGE HOUSE, 319 Pinner Road, North Harrow, Harrow, received 4 Aug 2023 — approved on 29 Nov 2023 (delegated, Fergus Freeney).

HarrowNorth HarrowP/2278/23
ApprovedRefusedOther
At a glance · this applicationHarrow profile →
Approved
Outcome
29 Nov 2023
17 wks
Decision time
9 wks over the 8-week target
Conditions
not captured
23
Documents
23 linked
Objections
not captured
No
Appeal
none recorded
Record from the Harrow planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Installation of ductwork to roof with associated plant work; Installation of sub station at rear; ancillary works

Reference
P/2278/23
Type
Full Planning Application
Applicant
Agent / consultant
Case officer
Council
Received
4 Aug 2023
Validated
8 Sep 2023
Target date
29 Nov 2023
Decision date
29 Nov 2023
Decision route
Delegated (officer)
Status
Decision Issued
Reference
P/2278/23
Type
Full Planning Application
Show all 15 rows
Applicant
Agent / consultant
Case officer
Council
Received
4 Aug 2023
Validated
8 Sep 2023
Target date
29 Nov 2023
Decision date
29 Nov 2023
Decision route
Delegated (officer)
Status
Decision Issued
Documents

What was filed?

Document
Published
View
DN - FULL and HSE Granted
29 Nov 2023
Officer Report
1 Nov 2023
PL Application Supporting Documents
21 Sept 2023
SITE NOTICE
21 Sept 2023
SITE NOTICE
21 Sept 2023
PL Application - Full Planning Permission - Redacted
21 Sept 2023
PL Existing Ground Floor Plan
8 Aug 2023
PL Proposed Ground Floor Plan
8 Aug 2023
PL Existing Roof Plan
8 Aug 2023
PL Proposed Roof Plan
8 Aug 2023
DN - FULL and HSE Granted
29 Nov 2023
Officer Report
1 Nov 2023
PL Application Supporting Documents
21 Sept 2023
Show all 10 rows
SITE NOTICE
21 Sept 2023
SITE NOTICE
21 Sept 2023
PL Application - Full Planning Permission - Redacted
21 Sept 2023
PL Existing Ground Floor Plan
8 Aug 2023
PL Proposed Ground Floor Plan
8 Aug 2023
PL Existing Roof Plan
8 Aug 2023
PL Proposed Roof Plan
8 Aug 2023

Documents open on the Harrow portal. View the application page ↗

Decision

What happened?

Approved on 29 Nov 2023, delegated decision by Fergus Freeney — 17 weeks from submission (9 over the 8-week target).

Timeline

Date
Event
4 Aug 2023
Application received
8 Sep 2023
Application validated
29 Nov 2023
Statutory target date
29 Nov 2023
Delegated decision: Approved · Fergus Freeney
4 Aug 2023
Application received
8 Sep 2023
Application validated
29 Nov 2023
Statutory target date
Show all 4 rows
29 Nov 2023
Delegated decision: Approved · Fergus Freeney

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.