34305/APP/2025/1608.
UXBRIDGE UNDERGROUND STATION HIGH STREET UXBRIDGE UB8 1RJ
Full / Other Planning at UXBRIDGE UNDERGROUND STATION HIGH STREET UXBRIDGE UB8 1RJ, received 10 Jun 2025 — approved on 1 Sep 2025 (delegated, Christos Chrysanthou).
What is it?
Installation of new One Person Operations (OPO) cameras, brackets etc. for a new Platform-Train Interface System with retention and eventually removal of existing OPO cameras, brackets etc. to enable the introduction of new rolling stock to the Piccadilly Line as part of the Piccadilly Line Upgrade
Show all 15 rows
What was filed?
Documents open on the Hillingdon portal. View the application page ↗
What happened?
Approved on 1 Sep 2025, delegated decision by Christos Chrysanthou — 12 weeks from submission (4 over the 8-week target).
Timeline
Public response
Comment counts were not captured for this application.
Who is involved?
What affects it?
Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.
Other applications within 250 metres (context — nearby, not this application)
No other geocoded decision is recorded within 250 metres.