Planning Atlas
Planning AtlasIslingtonClerkenwell wardP2025/0807/FUL
Planning application · Islington

P2025/0807/FUL.

33 - 39 Bowling Green Lane, London

Full / Other Planning at 33 - 39 Bowling Green Lane, London, received 20 Mar 2025 — approved on 11 Jun 2025 (delegated, Megan Stevens).

IslingtonClerkenwellP2025/0807/FUL
ApprovedRefusedOther
At a glance · this applicationIslington profile →
Approved
Outcome
11 Jun 2025
12 wks
Decision time
4 wks over the 8-week target
6
Conditions
attached to the decision
17
Documents
17 linked
Objections
not captured
No
Appeal
none recorded
Record from the Islington planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Installation of 2no. air source heat pumps, 2no. mechanical ventilation with heat recovery units and associated equipment at roof level. Extension of guardrail at roof level. Replacement of existing atrium roof vents with new automatic openable vents. Installation of vents and louvre panels on rear elevation.

Reference
P2025/0807/FUL
Type
Full Planning Application
Applicant
Agent / consultant
Case officer
Council
Received
20 Mar 2025
Validated
17 Apr 2025
Target date
11 Jun 2025
Decision date
11 Jun 2025
Decision route
Delegated (officer)
Status
FINAL DECISION
Reference
P2025/0807/FUL
Type
Full Planning Application
Show all 15 rows
Applicant
Agent / consultant
Case officer
Council
Received
20 Mar 2025
Validated
17 Apr 2025
Target date
11 Jun 2025
Decision date
11 Jun 2025
Decision route
Delegated (officer)
Status
FINAL DECISION
Documents

What was filed?

Document
Published
View
Application Form - Without Personal Data
20 Mar 2025
The location plan
20 Mar 2025
Site/Block Plan - Existing
20 Mar 2025
First Floor Plan - Existing
20 Mar 2025
Roof Plan - Existing
20 Mar 2025
Elevation (Front) - Existing
20 Mar 2025
Elevation (Rear) - Existing
20 Mar 2025
First Floor Plan - Proposed
20 Mar 2025
Community Infrastructure Levy - Completed form
20 Mar 2025
Sustainable Design & Construction Statement
14 Apr 2025
Application Form - Without Personal Data
20 Mar 2025
The location plan
20 Mar 2025
Site/Block Plan - Existing
20 Mar 2025
Show all 10 rows
First Floor Plan - Existing
20 Mar 2025
Roof Plan - Existing
20 Mar 2025
Elevation (Front) - Existing
20 Mar 2025
Elevation (Rear) - Existing
20 Mar 2025
First Floor Plan - Proposed
20 Mar 2025
Community Infrastructure Levy - Completed form
20 Mar 2025
Sustainable Design & Construction Statement
14 Apr 2025

Documents open on the Islington portal. View the application page ↗

Decision

What happened?

Approved on 11 Jun 2025, delegated decision by Megan Stevens — 12 weeks from submission (4 over the 8-week target).

Timeline

Date
Event
20 Mar 2025
Application received
17 Apr 2025
Application validated
11 Jun 2025
Statutory target date
11 Jun 2025
Delegated decision: Approved · Megan Stevens
20 Mar 2025
Application received
17 Apr 2025
Application validated
11 Jun 2025
Statutory target date
Show all 4 rows
11 Jun 2025
Delegated decision: Approved · Megan Stevens

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.