Planning Atlas
Planning AtlasIslingtonHighbury wardP2025/2161/LBC
Planning application · Islington

P2025/2161/LBC.

Clock Tower, Highbury Hill, London, N5 1BA

Listed Building at Clock Tower, Highbury Hill, London, N5 1BA, received 28 Jul 2025 — approved on 23 Mar 2026 by committee.

IslingtonHighburyN5 1BAP2025/2161/LBC
ApprovedRefusedOther
At a glance · this applicationIslington profile →
Approved
Outcome
23 Mar 2026
34 wks
Decision time
26 wks over the 8-week target
12
Conditions
attached to the decision
17
Documents
17 linked
Objections
not captured
No
Appeal
none recorded
Record from the Islington planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Dismantle the Clock Tower, remove to undertake conservation refurbishment of the Clock Tower and return and reinstall onto the hexagonal plinth on which it sits at present. (Reconsultation updated location plan, design and access statement and heritage statement).

Reference
P2025/2161/LBC
Type
Listed Building
Applicant
Agent / consultant
None recorded
Case officer
Postcode
N5 1BA
Council
Received
28 Jul 2025
Validated
28 Aug 2025
Target date
14 Oct 2025
Decision date
23 Mar 2026
Decision route
Planning committee
Status
FINAL DECISION
Reference
P2025/2161/LBC
Type
Listed Building
Show all 16 rows
Applicant
Agent / consultant
None recorded
Case officer
Postcode
N5 1BA
Council
Received
28 Jul 2025
Validated
28 Aug 2025
Target date
14 Oct 2025
Decision date
23 Mar 2026
Decision route
Planning committee
Status
FINAL DECISION
Documents

What was filed?

Document
Published
View
The location plan
28 Jul 2025
Proposed works drawing
28 Jul 2025
Ecological survey
28 Jul 2025
Paint decoration analysis
28 Jul 2025
Photograph of road
28 Jul 2025
Hoardings
28 Jul 2025
Heritage statement - after redaction
8 Aug 2025
Lead Paint Sampling - after redaction
8 Aug 2025
Design and access statement- after redaction
8 Aug 2025
Redacted revised application form
27 Aug 2025
The location plan
28 Jul 2025
Proposed works drawing
28 Jul 2025
Ecological survey
28 Jul 2025
Show all 10 rows
Paint decoration analysis
28 Jul 2025
Photograph of road
28 Jul 2025
Hoardings
28 Jul 2025
Heritage statement - after redaction
8 Aug 2025
Lead Paint Sampling - after redaction
8 Aug 2025
Design and access statement- after redaction
8 Aug 2025
Redacted revised application form
27 Aug 2025

Documents open on the Islington portal. View the application page ↗

Decision

What happened?

Approved on 23 Mar 2026, determined by the planning committee — 34 weeks from submission (26 over the 8-week target).

Timeline

Date
Event
28 Jul 2025
Application received
28 Aug 2025
Application validated
14 Oct 2025
Statutory target date
23 Mar 2026
Committee decision: Approved
28 Jul 2025
Application received
28 Aug 2025
Application validated
14 Oct 2025
Statutory target date
Show all 4 rows
23 Mar 2026
Committee decision: Approved

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
No agent recorded
Applied without an agent, or agent not recorded.
Case officer (report to committee)
Determined at committee
Applicant — the party who applied, not necessarily the owner
No agent recorded
Applied without an agent, or agent not recorded.
Case officer (report to committee)
Show all 4 rows
Determined at committee
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.