P2026/0160/FUL.

Ground Floor Flat, 78 Highbury Park, London

Full / Other Planning at Ground Floor Flat, 78 Highbury Park, London, received 21 Jan 2026 — approved on 26 May 2026 (delegated, Cyrus Wong).

IslingtonHighburyP2026/0160/FUL
ApprovedRefusedOther
At a glance · this applicationIslington profile →
Approved
Outcome
26 May 2026
18 wks
Decision time
10 wks over the 8-week target
3
Conditions
attached to the decision
13
Documents
13 linked
0
Objections
not captured
No
Appeal
none recorded
Record from the Islington planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Replacement of roof and rear doors of existing single-storey rear extension.

Reference
P2026/0160/FUL
Type
Full Planning Application
Applicant
Agent / consultant
Case officer
Council
Received
21 Jan 2026
Validated
25 Feb 2026
Target date
21 Apr 2026
Decision date
26 May 2026
Decision route
Delegated (officer)
Status
FINAL DECISION
Reference
P2026/0160/FUL
Type
Full Planning Application
Show all 16 rows
Applicant
Agent / consultant
Case officer
Council
Received
21 Jan 2026
Validated
25 Feb 2026
Target date
21 Apr 2026
Decision date
26 May 2026
Decision route
Delegated (officer)
Status
FINAL DECISION
Documents

What was filed?

Document
Published
View
OS Plan - Block Plan
21 Jan 2026
Fire Strategy
21 Jan 2026
Proposed Elevation
21 Jan 2026
Block Plan
21 Jan 2026
Existing Plan and Elevation
21 Jan 2026
OS Plan - Location Plan
21 Jan 2026
Proposed Glazing Details
25 Feb 2026
Sustainable Design and Construction Statement
25 Feb 2026
Proposed Plan
25 Feb 2026
Existing and Proposed Roof Plan
25 Feb 2026
OS Plan - Block Plan
21 Jan 2026
Fire Strategy
21 Jan 2026
Proposed Elevation
21 Jan 2026
Show all 10 rows
Block Plan
21 Jan 2026
Existing Plan and Elevation
21 Jan 2026
OS Plan - Location Plan
21 Jan 2026
Proposed Glazing Details
25 Feb 2026
Sustainable Design and Construction Statement
25 Feb 2026
Proposed Plan
25 Feb 2026
Existing and Proposed Roof Plan
25 Feb 2026

Documents open on the Islington portal. View the application page ↗

Decision

What happened?

Approved on 26 May 2026, delegated decision by Cyrus Wong — 18 weeks from submission (10 over the 8-week target).

Timeline

Date
Event
21 Jan 2026
Application received
25 Feb 2026
Application validated
21 Apr 2026
Statutory target date
26 May 2026
Delegated decision: Approved · Cyrus Wong
21 Jan 2026
Application received
25 Feb 2026
Application validated
21 Apr 2026
Statutory target date
Show all 4 rows
26 May 2026
Delegated decision: Approved · Cyrus Wong

Public response

Measure
Count
Objections
0
Objections
0
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.