2023/4015.
Phase 6: Battersea Power Station Cringle Street SW11 8BX
Full / Other Planning at Phase 6: Battersea Power Station Cringle Street SW11 8BX, received 3 Nov 2023 — approved on 3 Apr 2024 by committee.
What is it?
Installation of temporary structures for 5 years comprising an indoor leisure and recreation facility (Class E(d)) and an exhibition hall (Class F1(e)), provision of a temporary structure for use as a cafe (Class E(b)) alongside a temporary sub-station and use of the existing shipping containers as toilet and changing facilities and a cafe (Class E(b)) in association with the indoor leisure and recreation facility (Class E(d)) as well as other associated and enabling works to include external landscaping, lighting, fencing, servicing and access arrangements.
Show all 14 rows
What was filed?
Documents open on the Wandsworth portal. View the application page ↗
What happened?
Approved on 3 Apr 2024, determined by the planning committee — 22 weeks from submission (14 over the 8-week target).
Timeline
Public response
Comment counts were not captured for this application.
Who is involved?
Show all 4 rows
What affects it?
Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.
Other applications within 250 metres (context — nearby, not this application)
No other geocoded decision is recorded within 250 metres.