24/07491/LBC.

129 Harley Street London W1G 6BA

Listed Building at 129 Harley Street London W1G 6BA, received 28 Oct 2024 — approved on 11 Feb 2025 (delegated, Matthew Giles).

WestminsterMaryleboneW1G 6BA24/07491/LBC
ApprovedRefusedOther
At a glance · this applicationWestminster profile →
Approved
Outcome
11 Feb 2025
15 wks
Decision time
7 wks over the 8-week target
Conditions
not captured
96
Documents
96 linked
0
Objections
0 in support
No
Appeal
none recorded
Record from the Westminster planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Internal alterations at lower ground, and ground floor levels including lowering of the floor slab throughout. Replacement flat roof coverings at first and third floor levels and replacement slate roof at main roof level. Alterations to the rear mews frontage. Installation of plant in the rear lightwell between the main property and the mews property to the rear. (Linked with 24/07490/FULL)

Reference
24/07491/LBC
Type
Listed Building Consent Application
Agent / consultant
Case officer
Postcode
Received
28 Oct 2024
Validated
5 Nov 2024
Target date
31 Dec 2024
Decision date
11 Feb 2025
Decision route
Delegated (officer)
Status
Decided
Reference
24/07491/LBC
Type
Listed Building Consent Application
Show all 16 rows
Agent / consultant
Case officer
Postcode
Received
28 Oct 2024
Validated
5 Nov 2024
Target date
31 Dec 2024
Decision date
11 Feb 2025
Decision route
Delegated (officer)
Status
Decided
Documents

What was filed?

Document
Published
View
GRANT OF LISTED BUILDING CONSENT [PE]
11 Feb 2025
DELEGATED REPORT
11 Feb 2025
EXISTING GROUND FLOOR PLAN
22 Jan 2025
GROUND FLOOR PLAN ? DEMOLITION
22 Jan 2025
PROPOSED GROUND FLOOR PLAN
22 Jan 2025
PROPOSED FIRST FLOOR PLAN
22 Jan 2025
PROPOSED SECOND FLOOR PLAN
22 Jan 2025
THIRD FLOOR PLAN - DEMOLITION
22 Jan 2025
PROPOSED THIRD FLOOR PLAN
22 Jan 2025
EXISTING LOWER GROUND FLOOR PLAN
22 Jan 2025
GRANT OF LISTED BUILDING CONSENT [PE]
11 Feb 2025
DELEGATED REPORT
11 Feb 2025
EXISTING GROUND FLOOR PLAN
22 Jan 2025
Show all 10 rows
GROUND FLOOR PLAN ? DEMOLITION
22 Jan 2025
PROPOSED GROUND FLOOR PLAN
22 Jan 2025
PROPOSED FIRST FLOOR PLAN
22 Jan 2025
PROPOSED SECOND FLOOR PLAN
22 Jan 2025
THIRD FLOOR PLAN - DEMOLITION
22 Jan 2025
PROPOSED THIRD FLOOR PLAN
22 Jan 2025
EXISTING LOWER GROUND FLOOR PLAN
22 Jan 2025

Documents open on the Westminster portal (the portal needs its documents tab opened first — the link handles that). View the application page ↗

Decision

What happened?

Approved on 11 Feb 2025, delegated decision by Matthew Giles — 15 weeks from submission (7 over the 8-week target).

Timeline

Date
Event
28 Oct 2024
Application received
5 Nov 2024
Application validated
31 Dec 2024
Statutory target date
11 Feb 2025
Delegated decision: Approved · Matthew Giles
28 Oct 2024
Application received
5 Nov 2024
Application validated
31 Dec 2024
Statutory target date
Show all 4 rows
11 Feb 2025
Delegated decision: Approved · Matthew Giles

Public response

Measure
Count
Objections
0
In support
0
Total comments
0
Objections
0
In support
0
Total comments
0
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.