Planning Atlas
Planning AtlasBarnetTotteridge & Woodside ward23/2598/FUL
Planning application · Barnet

23/2598/FUL.

Land Adjacent To The National Grid Sub-station Partingdale Lane London NW7 1NS

Full / Other Planning at Land Adjacent To The National Grid Sub-station Partingdale Lane London NW7 1NS, received 15 Jun 2023 — approved on 14 Jun 2024 by committee.

BarnetTotteridge & WoodsideNW7 1NS23/2598/FUL
ApprovedRefusedOther
At a glance · this applicationBarnet profile →
Approved
Outcome
14 Jun 2024
52 wks
Decision time
44 wks over the 8-week target
Conditions
not captured
28
Documents
28 linked
13
Objections
0 in support
No
Appeal
none recorded
Record from the Barnet planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Installation of a fibre optic cable route, hydrant connection route and drainage connection pipe for the approved Mill Hill Battery Storage Facility

Reference
23/2598/FUL
Type
Full Application
Agent / consultant
Case officer
Postcode
NW7 1NS
Council
Received
15 Jun 2023
Target date
10 Aug 2023
Decision date
14 Jun 2024
Decision route
Planning committee
Status
Approved subject to conditions
Reference
23/2598/FUL
Type
Full Application
Show all 15 rows
Agent / consultant
Case officer
Postcode
NW7 1NS
Council
Received
15 Jun 2023
Target date
10 Aug 2023
Decision date
14 Jun 2024
Decision route
Planning committee
Status
Approved subject to conditions
Documents

What was filed?

Document
Published
View
DN: APPROVE FUL WITH CONDS
14 Jun 2024
AIA UTILITY APP
9 Apr 2024
AMS UTILITY APP
9 Apr 2024
ECOLOGY REPORT
20 Nov 2023
PARTINGDALE LODGE
8 Sept 2023
PARTINGDALE LODGE
8 Sept 2023
PARTINGDALE LODGE
7 Sept 2023
PARTINGDALE LODGE
25 Jul 2023
COMMENT(FULL)
18 Jul 2023
COMMENT(FULL)
10 Jul 2023
DN: APPROVE FUL WITH CONDS
14 Jun 2024
AIA UTILITY APP
9 Apr 2024
AMS UTILITY APP
9 Apr 2024
Show all 10 rows
ECOLOGY REPORT
20 Nov 2023
PARTINGDALE LODGE
8 Sept 2023
PARTINGDALE LODGE
8 Sept 2023
PARTINGDALE LODGE
7 Sept 2023
PARTINGDALE LODGE
25 Jul 2023
COMMENT(FULL)
18 Jul 2023
COMMENT(FULL)
10 Jul 2023

Documents open on the Barnet portal (the portal needs its documents tab opened first — the link handles that). View the application page ↗

Decision

What happened?

Approved on 14 Jun 2024, determined by the planning committee — 52 weeks from submission (44 over the 8-week target).

Timeline

Date
Event
15 Jun 2023
Application received
10 Aug 2023
Statutory target date
14 Jun 2024
Committee decision: Approved
15 Jun 2023
Application received
10 Aug 2023
Statutory target date
14 Jun 2024
Committee decision: Approved

Public response

Measure
Count
Objections
13
In support
0
Total comments
13
Objections
13
In support
0
Total comments
13
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Determined at committee
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Show all 4 rows
Determined at committee
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.