Full / Other Planning at Land West Of Meridian Water Station, South Of A406, Fore Street, Edmonton Enfield N18, received 5 Aug 2022 — approved on 19 Dec 2022 by committee.

EnfieldUpper Edmonton22/02777/FUL
ApprovedRefusedOther
At a glance · this applicationEnfield profile →
Approved
Outcome
19 Dec 2022
19 wks
Decision time
11 wks over the 8-week target
Conditions
not captured
57
Documents
57 linked
0
Objections
0 in support
No
Appeal
none recorded
Record from the Enfield planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Phase 2 Part 1 of new 23km Borough-wide district heating distribution network in Enfield comprising at this stage pipework of approximately 2km in length.

Reference
22/02777/FUL
Type
Full
Agent / consultant
Case officer
Council
Received
5 Aug 2022
Validated
19 Aug 2022
Target date
18 Nov 2022
Decision date
19 Dec 2022
Decision route
Planning committee
Status
Decided
Reference
22/02777/FUL
Type
Full
Show all 15 rows
Agent / consultant
Case officer
Council
Received
5 Aug 2022
Validated
19 Aug 2022
Target date
18 Nov 2022
Decision date
19 Dec 2022
Decision route
Planning committee
Status
Decided
Documents

What was filed?

Document
Published
View
Decision Notice
19 Dec 2022
Arboricultural Impact Assessment (Reivsed)
22 Nov 2022
1665-ENF-D3A-00-XX-DR-M-270-004
19 Aug 2022
1665 d3a Phase 2 Part 1 Drawing Transmittal sheet-001
19 Aug 2022
Application Form - Without Personal Data
5 Aug 2022
Flood risk assessment
5 Aug 2022
DETAILED UNEXPLODED ORDNANCE (UXO)
5 Aug 2022
Other relevant information
5 Aug 2022
Other relevant information
5 Aug 2022
Heritage statement
5 Aug 2022
Decision Notice
19 Dec 2022
Arboricultural Impact Assessment (Reivsed)
22 Nov 2022
1665-ENF-D3A-00-XX-DR-M-270-004
19 Aug 2022
Show all 10 rows
1665 d3a Phase 2 Part 1 Drawing Transmittal sheet-001
19 Aug 2022
Application Form - Without Personal Data
5 Aug 2022
Flood risk assessment
5 Aug 2022
DETAILED UNEXPLODED ORDNANCE (UXO)
5 Aug 2022
Other relevant information
5 Aug 2022
Other relevant information
5 Aug 2022
Heritage statement
5 Aug 2022

Documents open on the Enfield portal (the portal needs its documents tab opened first — the link handles that). View the application page ↗

Decision

What happened?

Approved on 19 Dec 2022, determined by the planning committee — 19 weeks from submission (11 over the 8-week target).

Timeline

Date
Event
5 Aug 2022
Application received
19 Aug 2022
Application validated
18 Nov 2022
Statutory target date
19 Dec 2022
Committee decision: Approved
5 Aug 2022
Application received
19 Aug 2022
Application validated
18 Nov 2022
Statutory target date
Show all 4 rows
19 Dec 2022
Committee decision: Approved

Public response

Measure
Count
Objections
0
In support
0
Total comments
0
Objections
0
In support
0
Total comments
0
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Determined at committee
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Show all 4 rows
Determined at committee
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.