Planning Atlas
Planning application · Enfield

P12-00559PLA.

New Cottage Farm, The Ridgeway, Enfield, EN6 5QT

Full / Other Planning at New Cottage Farm, The Ridgeway, Enfield, EN6 5QT, received 5 Mar 2012 — withdrawn on 8 Feb 2023 (delegated, Sean Newton).

EnfieldEN6 5QTP12-00559PLA
ApprovedRefusedOther
At a glance · this applicationEnfield profile →
Withdrawn
Outcome
8 Feb 2023
570 wks
Decision time
562 wks over the 8-week target
Conditions
not captured
12
Documents
12 linked
0
Objections
0 in support
No
Appeal
none recorded
Record from the Enfield planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Construction of a 6 metre high bund to north of site, adjacent to M25.

Reference
P12-00559PLA
Type
Full
Applicant
Agent / consultant
Case officer
Postcode
EN6 5QT
Ward
Not recorded
Council
Received
5 Mar 2012
Validated
5 Apr 2012
Target date
31 May 2012
Decision date
8 Feb 2023
Decision route
Delegated (officer)
Status
Application Withdrawn
Reference
P12-00559PLA
Type
Full
Show all 16 rows
Applicant
Agent / consultant
Case officer
Postcode
EN6 5QT
Ward
Not recorded
Council
Received
5 Mar 2012
Validated
5 Apr 2012
Target date
31 May 2012
Decision date
8 Feb 2023
Decision route
Delegated (officer)
Status
Application Withdrawn
Documents

What was filed?

Document
Published
View
APPLICATION FORM DATED 16-01-12
5 Apr 2012
LOCATION PLAN
5 Apr 2012
NEW COTTAGE FARM BUND WALLS - METHOD STATEMENT FOR CONSTRUCT
5 Apr 2012
BUND CROSS SECTION
5 Apr 2012
MAP 1 & 2 OF PIPES AND CABLES OWNED BY NATONAL GRID GAS & NA
5 Apr 2012
NATIONAL GRID DESIGN AND ACCESS STATEMENT
5 Apr 2012
STATEMENT LETTER FROM HIGHWAY AGENCY DATED 14-05-12
5 Apr 2012
EMAILS DATED FROM 20-04-12 TO 07-08-12
5 Apr 2012
HIGHWAYS AGENCY 09-07-12
5 Apr 2012
PLANNING CONSULTATION RESPONCE
5 Apr 2012
APPLICATION FORM DATED 16-01-12
5 Apr 2012
LOCATION PLAN
5 Apr 2012
NEW COTTAGE FARM BUND WALLS - METHOD STATEMENT FOR CONSTRUCT
5 Apr 2012
Show all 10 rows
BUND CROSS SECTION
5 Apr 2012
MAP 1 & 2 OF PIPES AND CABLES OWNED BY NATONAL GRID GAS & NA
5 Apr 2012
NATIONAL GRID DESIGN AND ACCESS STATEMENT
5 Apr 2012
STATEMENT LETTER FROM HIGHWAY AGENCY DATED 14-05-12
5 Apr 2012
EMAILS DATED FROM 20-04-12 TO 07-08-12
5 Apr 2012
HIGHWAYS AGENCY 09-07-12
5 Apr 2012
PLANNING CONSULTATION RESPONCE
5 Apr 2012

Documents open on the Enfield portal (the portal needs its documents tab opened first — the link handles that). View the application page ↗

Decision

What happened?

Withdrawn on 8 Feb 2023, delegated decision by Sean Newton — 570 weeks from submission (562 over the 8-week target).

Timeline

Date
Event
5 Mar 2012
Application received
5 Apr 2012
Application validated
31 May 2012
Statutory target date
8 Feb 2023
Delegated decision: Withdrawn · Sean Newton
5 Mar 2012
Application received
5 Apr 2012
Application validated
31 May 2012
Statutory target date
Show all 4 rows
8 Feb 2023
Delegated decision: Withdrawn · Sean Newton

Public response

Measure
Count
Objections
0
In support
0
Total comments
0
Objections
0
In support
0
Total comments
0
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.