Planning AtlasHackneyQueensbridge (O) wardE8 4QS4 - 6 Sheep Lane, Hackney, London, E8 4QS2009/0033
Planning application · Hackney

2009/0033.

4 - 6 Sheep Lane, Hackney, London, E8 4QS

Discharge of Conditions at 4 - 6 Sheep Lane, Hackney, London, E8 4QS, received 8 Jan 2009 — approved on 8 Apr 2009 by committee.

ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
8 Apr 2009
13 wks
Decision time
5 wks over the 8-week target
Conditions
not captured
31
Documents
31 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Section 73 application for variation of condition 17 of planning permission 2006/0721: erection of a 6 storey plus basement building to provide 45 residential units ( 10 x 1 bed, 20 x 2 bed, 7 x 3 bed and 8 x 4 bed) and 2350 sqm of class B1 (office) floorspace. Variation relates to revised elevation

Reference
2009/0033
Type
Removal/Variation of Condition(s)
Agent / consultant
Case officer
Postcode
Council
Received
8 Jan 2009
Target date
9 Apr 2009
Decision date
8 Apr 2009
Decision route
Planning committee
Status
Final Decision
Reference
2009/0033
Type
Removal/Variation of Condition(s)
Show all 16 rows
Agent / consultant
Case officer
Postcode
Council
Received
8 Jan 2009
Target date
9 Apr 2009
Decision date
8 Apr 2009
Decision route
Planning committee
Status
Final Decision
Documents

What was filed?

Document
Published
View
2009/0033 Planning -
2009/0033 Planning - 4TH FLOOR PLAN
2009/0033 Planning - ELEVATION C WEST ELEVATION
2009/0033 Planning -
2009/0033 Planning - GROUND FLOOR PLAN
2009/0033 Planning - ELEVATION A EAST ELEVATION
2009/0033 Planning - ROOF PLAN
2009/0033 Planning - ROOF PLAN
2009/0033 Planning - ELEVATION B NORTH ELEVATION
2009/0033 Planning - 5TH FLOOR PLAN
2009/0033 Planning -
2009/0033 Planning - 4TH FLOOR PLAN
2009/0033 Planning - ELEVATION C WEST ELEVATION
Show all 10 rows
2009/0033 Planning -
2009/0033 Planning - GROUND FLOOR PLAN
2009/0033 Planning - ELEVATION A EAST ELEVATION
2009/0033 Planning - ROOF PLAN
2009/0033 Planning - ROOF PLAN
2009/0033 Planning - ELEVATION B NORTH ELEVATION
2009/0033 Planning - 5TH FLOOR PLAN

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 8 Apr 2009, determined by the planning committee — 13 weeks from submission (5 over the 8-week target).

Timeline

Date
Event
8 Jan 2009
Application received
9 Apr 2009
Statutory target date
8 Apr 2009
Committee decision: Approved
8 Jan 2009
Application received
9 Apr 2009
Statutory target date
8 Apr 2009
Committee decision: Approved

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Determined at committee
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer (report to committee)
Show all 4 rows
Determined at committee
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.