2022/2370.

74 Malvern Road, Hackney, London, E8 3LJ

Householder at 74 Malvern Road, Hackney, London, E8 3LJ, received 28 Sep 2022 — approved on 21 Dec 2022 (delegated, Jonathan Bainbridge).

ApprovedRefusedOther
At a glance · this applicationHackney profile →
Approved
Outcome
21 Dec 2022
12 wks
Decision time
4 wks over the 8-week target
Conditions
not captured
7
Documents
7 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hackney planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Ground floor single storey side and rear extension. Replacement of existing windows, addition of rooflight to rear slope and windows to flank elevation, widening of steps to lower ground floor. Removal of all existing trees in the rear garden and Monkey Puzzle tree in front garden.

Reference
2022/2370
Type
Householder Planning
Agent / consultant
Postcode
Council
Received
28 Sep 2022
Validated
3 Oct 2022
Target date
21 Dec 2022
Decision date
21 Dec 2022
Decision route
Delegated (officer)
Status
Final Decision
Reference
2022/2370
Type
Householder Planning
Show all 17 rows
Agent / consultant
Postcode
Council
Received
28 Sep 2022
Validated
3 Oct 2022
Target date
21 Dec 2022
Decision date
21 Dec 2022
Decision route
Delegated (officer)
Status
Final Decision
Documents

What was filed?

Document
Published
View
DN-Householder Granted Final
21 Dec 2022
Officer Report
20 Dec 2022
165 - Existing Drawings
29 Sept 2022
Design and access statement
29 Sept 2022
AIA TCP TPP
29 Sept 2022
Community Infrastructure Levy - Completed form
29 Sept 2022
Application Form - Without Personal Data
29 Sept 2022
DN-Householder Granted Final
21 Dec 2022
Officer Report
20 Dec 2022
165 - Existing Drawings
29 Sept 2022
Show all 7 rows
Design and access statement
29 Sept 2022
AIA TCP TPP
29 Sept 2022
Community Infrastructure Levy - Completed form
29 Sept 2022
Application Form - Without Personal Data
29 Sept 2022

Documents open on the Hackney portal. View the application page ↗

Decision

What happened?

Approved on 21 Dec 2022, delegated decision by Jonathan Bainbridge — 12 weeks from submission (4 over the 8-week target).

Timeline

Date
Event
28 Sep 2022
Application received
3 Oct 2022
Application validated
21 Dec 2022
Statutory target date
21 Dec 2022
Delegated decision: Approved · Jonathan Bainbridge
28 Sep 2022
Application received
3 Oct 2022
Application validated
21 Dec 2022
Statutory target date
Show all 4 rows
21 Dec 2022
Delegated decision: Approved · Jonathan Bainbridge

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.