Full / Other Planning at Charing Cross Hospital Fulham Palace Road London W6 8RF, received 6 Oct 2021 — approved on 19 Jul 2022 (delegated, Mwansa Tembo).
Record from the Hammersmith And Fulham planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application
What is it?
Installation and screening of 2no. new air source combo heat pumps on the roof of the Oncology Building; installation and screening of 2no. new air source combo heat pumps on the roof of the X-ray Building; installation of an external plant area on a raised deck adjacent to the Tower block; installation of a new substation; and installation of pipework to existing external fabric to serve all new heat pumps, including to the full extent of the north elevation of the Tower Block from ground up to the 17th floor.
Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.
Other applications within 250 metres (context — nearby, not this application)
No other geocoded decision is recorded within 250 metres.