Planning Atlas
Planning AtlasHammersmith And FulhamCollege Park And Old Oak ward2024/02816/DET
Planning application · Hammersmith And Fulham

2024/02816/DET.

Former Dairy Crest Site Land Beneath And Bounded By Westway And West London Railway Line And Adjoining 58 Wood Lane London W12

Discharge of Conditions at Former Dairy Crest Site Land Beneath And Bounded By Westway And West London Railway Line And Adjoining 58 Wood Lane London W12, received 4 Nov 2024 — approved on 12 Feb 2026 (delegated, Jesenka Oezdalga).

ApprovedRefusedOther
At a glance · this applicationHammersmith And Fulham profile →
Approved
Outcome
12 Feb 2026
66 wks
Decision time
58 wks over the 8-week target
Conditions
not captured
6
Documents
6 linked
Objections
not captured
No
Appeal
none recorded
Record from the Hammersmith And Fulham planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Details to partially discharge Condition 28 (water network) in relation to Development Zone 1 (Phase 1); of Outline Planning Permission (ref: 2018/00267/OUT) dated 28 April 2021; (as amended by Non-Material Amendment application ref. 2024/00986/NMAT).

Reference
2024/02816/DET
Type
Details to Meet Conditions Full/Outline
Agent / consultant
Case officer
Received
4 Nov 2024
Validated
5 Nov 2024
Target date
12 Feb 2029
Decision date
12 Feb 2026
Decision route
Not recorded
Status
Final Decision
Reference
2024/02816/DET
Type
Details to Meet Conditions Full/Outline
Show all 15 rows
Agent / consultant
Case officer
Received
4 Nov 2024
Validated
5 Nov 2024
Target date
12 Feb 2029
Decision date
12 Feb 2026
Decision route
Not recorded
Status
Final Decision
Documents

What was filed?

Document
Published
View
APPLICATIONFORMREDACTED
MODELLING-CLEAN-WATER-CAPACITY-REPORT
DZ1-CONDITION-28-COVER-LETTER
CAPACITY-REPORT
PER.-DETAILS-TO-MEET-COND.-FULL-OUT-APP
DELEGATED-OFFICER-REPORT
APPLICATIONFORMREDACTED
MODELLING-CLEAN-WATER-CAPACITY-REPORT
DZ1-CONDITION-28-COVER-LETTER
Show all 6 rows
CAPACITY-REPORT
PER.-DETAILS-TO-MEET-COND.-FULL-OUT-APP
DELEGATED-OFFICER-REPORT

Documents open on the Hammersmith And Fulham portal. View the application page ↗

Decision

What happened?

Approved on 12 Feb 2026, delegated decision by Jesenka Oezdalga — 66 weeks from submission (58 over the 8-week target).

Timeline

Date
Event
4 Nov 2024
Application received
5 Nov 2024
Application validated
12 Feb 2029
Statutory target date
12 Feb 2026
Delegated decision: Approved · Jesenka Oezdalga
4 Nov 2024
Application received
5 Nov 2024
Application validated
12 Feb 2029
Statutory target date
Show all 4 rows
12 Feb 2026
Delegated decision: Approved · Jesenka Oezdalga

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.