Discharge of Conditions at 69-71 Bondway London SW8 1SQ, received 23 Mar 2022 — approved on 17 Jun 2022 (delegated, Lauren Shallcross).

LambethVauxhallSW8 1SQ22/01067/DET
ApprovedRefusedOther
At a glance · this applicationLambeth profile →
Approved
Outcome
17 Jun 2022
12 wks
Decision time
4 wks over the 8-week target
Conditions
not captured
8
Documents
8 linked
0
Objections
0 in support
No
Appeal
none recorded
Record from the Lambeth planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Approval of details pursuant to Condition 35 (Energy Strategy) of planning permission 16/05309/VOC (Variation of condition 2 (Approved Plans) of planning permission 14/00601/FUL (Demolition of existing buildings and redevelopment of the site to provide a residential led mixed use development in a building part 24/part 50 storeys in height (+ 3 levels of basement) and comprising 728.5 sqm of ground floor commercial units (flexible use class A1, A2, A3 and A4) , 5,171 sqm of office floorspace (use class B1) and 450 residential units)) granted on 15.09.2017

Reference
22/01067/DET
Type
Approval of Details
Agent / consultant
Case officer
Postcode
Council
Received
23 Mar 2022
Target date
17 Jun 2022
Decision date
17 Jun 2022
Decision route
Delegated (officer)
Status
Decided
Reference
22/01067/DET
Type
Approval of Details
Show all 15 rows
Agent / consultant
Case officer
Postcode
Council
Received
23 Mar 2022
Target date
17 Jun 2022
Decision date
17 Jun 2022
Decision route
Delegated (officer)
Status
Decided
Documents

What was filed?

Document
Published
View
Decision Notice
17 Jun 2022
Delegated Register
17 Jun 2022
SAP COMPLIANCE 1
16 Jun 2022
UPDATED ENERGY STRATEGY
16 Jun 2022
SAP COMPLIANCE 2
16 Jun 2022
SAP COMPLIANCE 3
16 Jun 2022
SUPERSEDED AS BUILT? STAGE 5 ENERGY STRATEGY REPORT
23 Mar 2022
COVERING LETTER
23 Mar 2022
Decision Notice
17 Jun 2022
Delegated Register
17 Jun 2022
SAP COMPLIANCE 1
16 Jun 2022
Show all 8 rows
UPDATED ENERGY STRATEGY
16 Jun 2022
SAP COMPLIANCE 2
16 Jun 2022
SAP COMPLIANCE 3
16 Jun 2022
SUPERSEDED AS BUILT? STAGE 5 ENERGY STRATEGY REPORT
23 Mar 2022
COVERING LETTER
23 Mar 2022

Documents open on the Lambeth portal (the portal needs its documents tab opened first — the link handles that). View the application page ↗

Decision

What happened?

Approved on 17 Jun 2022, delegated decision by Lauren Shallcross — 12 weeks from submission (4 over the 8-week target).

Timeline

Date
Event
23 Mar 2022
Application received
17 Jun 2022
Statutory target date
17 Jun 2022
Delegated decision: Approved · Lauren Shallcross
23 Mar 2022
Application received
17 Jun 2022
Statutory target date
17 Jun 2022
Delegated decision: Approved · Lauren Shallcross

Public response

Measure
Count
Objections
0
In support
0
Total comments
0
Objections
0
In support
0
Total comments
0
People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.