Planning Atlas
Planning AtlasRedbridgeLoxford ward1690/25/01
Planning application · Redbridge

1690/25/01.

DEVELOPMENT SOUTH EAST SIDE OF AND REAR OF 25 JERSEY ROAD IN, Mayville Road, Ilford

Discharge of Conditions at DEVELOPMENT SOUTH EAST SIDE OF AND REAR OF 25 JERSEY ROAD IN, Mayville Road, Ilford, received 21 Oct 2025 — approved on 1 May 2026 (delegated, Jordan Tai).

RedbridgeLoxford1690/25/01
ApprovedRefusedOther
At a glance · this applicationRedbridge profile →
Approved
Outcome
1 May 2026
27 wks
Decision time
19 wks over the 8-week target
2
Conditions
attached to the decision
8
Documents
8 linked
Objections
not captured
No
Appeal
none recorded
Record from the Redbridge planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Discharge of conditions for approved permission 1690/25: Materials (Condition 4); Walls and Fences (Condition 9); and Lamppost (Condition 12). (Summary).

Reference
1690/25/01
Type
Discharge of Condition(s)
Agent / consultant
Case officer
Council
Received
21 Oct 2025
Validated
20 Nov 2025
Target date
16 Dec 2025
Decision date
1 May 2026
Decision route
Delegated (officer)
Status
Decision Despatched
Reference
1690/25/01
Type
Discharge of Condition(s)
Show all 15 rows
Agent / consultant
Case officer
Council
Received
21 Oct 2025
Validated
20 Nov 2025
Target date
16 Dec 2025
Decision date
1 May 2026
Decision route
Delegated (officer)
Status
Decision Despatched
Documents

What was filed?

Document
Published
View
Application form
21 Oct 2025
Proposed plan
21 Oct 2025
External materials summary
21 Oct 2025
Acme Single Camber Clay Plain Tile
21 Oct 2025
Clay plain tiles
21 Oct 2025
The Cissbury Red Multi.
21 Oct 2025
Officer report
1 May 2026
Decision notice
1 May 2026
Application form
21 Oct 2025
Proposed plan
21 Oct 2025
External materials summary
21 Oct 2025
Show all 8 rows
Acme Single Camber Clay Plain Tile
21 Oct 2025
Clay plain tiles
21 Oct 2025
The Cissbury Red Multi.
21 Oct 2025
Officer report
1 May 2026
Decision notice
1 May 2026

Documents open on the Redbridge portal. View the application page ↗

Decision

What happened?

Approved on 1 May 2026, delegated decision by Jordan Tai — 27 weeks from submission (19 over the 8-week target).

Timeline

Date
Event
21 Oct 2025
Application received
20 Nov 2025
Application validated
16 Dec 2025
Statutory target date
1 May 2026
Delegated decision: Approved · Jordan Tai
21 Oct 2025
Application received
20 Nov 2025
Application validated
16 Dec 2025
Statutory target date
Show all 4 rows
1 May 2026
Delegated decision: Approved · Jordan Tai

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.