Development At The Cauliflower 553, High Road, Ilford

Listed Building at Development At The Cauliflower 553, High Road, Ilford, received 4 Aug 2023 — approved on 17 Oct 2023 (delegated, Thomas Smith-Keary).

ApprovedRefusedOther
At a glance · this applicationRedbridge profile →
Approved
Outcome
17 Oct 2023
11 wks
Decision time
3 wks over the 8-week target
5
Conditions
attached to the decision
63
Documents
63 linked
Objections
not captured
No
Appeal
none recorded
Record from the Redbridge planning register as captured; documents link to the council's own files. Nearby applications are context, not part of this application.
Application

What is it?

Single storey rear and part two storey side extensions. Use of basement as a late-night bar. Conversion of second and third floors to contain 5no. self-contained (1 x 1, 3 x 2 and 1 x 3 bedrooms) flats with associated cycle and waste/refuse storage. Refurbishment works to building and roof. Internal alterations. Full Planning Permission sought under application reference 2312/23. (Summary).

Reference
2313/23
Type
Listed Building Consent
Agent / consultant
Case officer
Council
Received
4 Aug 2023
Validated
25 Aug 2023
Target date
17 Oct 2023
Decision date
17 Oct 2023
Decision route
Delegated (officer)
Status
Decision Despatched
Reference
2313/23
Type
Listed Building Consent
Show all 15 rows
Agent / consultant
Case officer
Council
Received
4 Aug 2023
Validated
25 Aug 2023
Target date
17 Oct 2023
Decision date
17 Oct 2023
Decision route
Delegated (officer)
Status
Decision Despatched
Documents

What was filed?

Document
Published
View
Sunlight/daylight assessment
7 Aug 2023
Environmental statement
7 Aug 2023
Noise impact assessment
7 Aug 2023
Transport assessment
7 Aug 2023
Cover letter
7 Aug 2023
Fire statement
7 Aug 2023
Supporting document
7 Aug 2023
Supporting document
7 Aug 2023
Supporting document
7 Aug 2023
Supporting document
7 Aug 2023
Sunlight/daylight assessment
7 Aug 2023
Environmental statement
7 Aug 2023
Noise impact assessment
7 Aug 2023
Show all 10 rows
Transport assessment
7 Aug 2023
Cover letter
7 Aug 2023
Fire statement
7 Aug 2023
Supporting document
7 Aug 2023
Supporting document
7 Aug 2023
Supporting document
7 Aug 2023
Supporting document
7 Aug 2023

Documents open on the Redbridge portal. View the application page ↗

Decision

What happened?

Approved on 17 Oct 2023, delegated decision by Thomas Smith-Keary — 11 weeks from submission (3 over the 8-week target).

Timeline

Date
Event
4 Aug 2023
Application received
25 Aug 2023
Application validated
17 Oct 2023
Statutory target date
17 Oct 2023
Delegated decision: Approved · Thomas Smith-Keary
4 Aug 2023
Application received
25 Aug 2023
Application validated
17 Oct 2023
Statutory target date
Show all 4 rows
17 Oct 2023
Delegated decision: Approved · Thomas Smith-Keary

Public response

Comment counts were not captured for this application.

People

Who is involved?

Name
Role
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Applicant — the party who applied, not necessarily the owner
Agent · consultant profile
Case officer — delegated decision
Place

What affects it?

Context around the site — not part of this application. Designations over the site: use the map's designations filter (conservation areas, listed buildings, Article 4, flood risk …). Decisions within 250 metres of the site are listed below — context, not this application.

Other applications within 250 metres (context — nearby, not this application)

No other geocoded decision is recorded within 250 metres.